Sunday, May 31, 2009

Muddy mornings and rainy afternoons.






The days are cloudy and deliver rain every afternoon. Nice cool weather for making blocks and working on the wall.

The Upward Bound classes will be starting on Tue and we are ready and willing. The wedged blocks will be used for making an horno.

Tuesday, May 19, 2009

Legalize Mud


Last weekend was the international adobe conference organized by Quentin Wilson and hardworking staff.

The presentations were varied and interesting. I gave a short talk about the goals of Adobe Para La Gente, a citizen based interest group that has to do with restoration of native architectures, and vernacular building techniques of New Mexico, and especially the use of natural materials. It was well recieved by this eclectic group. Many shared experiences with code reform and gave suggestions on how to proceed.

Friday, May 15, 2009

Domos y Arcos







The second seminar, Arches, Domes and Vaults, has ended and we celebrated our progress. The class was talented, motivated and able to coordinate the work. The dome is well built and will last a long time with proper maintenance.
The structure will be finished by a church group that will arrive in June. We were able to attend the first day of the wonderful International Adobe Conference organized by Quentin Wilson and his able staff. The muddy life is the good life!

Wednesday, May 13, 2009

May the Circle be Unbroken











The dome with an arched opening flows upward. The ground beneath the feet takes on another form. No cement, no metal, no petroleum products.








The Arches, Domes and Vaults class from NNMC has gone from a square to a circle. The merry mudders are enthusiastic and bring a range of skills that makes teaching the class easy. Give them a few pointers and turn them loose. Too bad it's only a four day class. This group might not be able to work on the top third of the sphere.








Sunday, May 10, 2009



The work on the dome will commence this coming Monday, in the meantime we are continuing restoration on the 300 year old chimayo house.

We have peeled and pulled the concrete covering from the inside walls. The ground level was wet from trapped moisture. But after a couple of weeks of breathing, the ground is drying and firming up. We have dug down past foundation level and will create a permanent breathing space. When the outside concrete shell is removed the structure will continue its drying and self healing, ready to begin yet another three hundred year cycle of noble service.

Tuesday, May 5, 2009

Walls and Oven


The merry mudders continue on their merry and muddy way. The walls are coming up from the foundation.



















Later during the day, an earth oven (horno) is being plastered with an experimental horse manure plaster. This is to replace the experimental mud plaster that didn't work very well last year. And such is the process of learning. We like to blame the plaster failure on the fact that the horno is built from asphalt adobe blocks. But this is probably not the case. We will build an horno this summer from earthen adobe blocks and do some comparisons.

Friday, May 1, 2009

Foundation for Dome




Blocks have been made and are curing. Building time.
The soaking pit is started while the dirt from the trench is mixed with water for mud to lay in the stones. A merry crew of buiders messing with mud...